Projects · Habshan gas processing plant, Abu Dhabi
Habshan CCUS
FID announced 6 September 2023. ADNOC states it will triple its carbon capture capacity to 2.3 Mt/yr. Expected start-up 2026.
Last verified:
Under constructionAs of 2026Confidence: High
- Location
- Habshan gas processing plant, Abu Dhabi
- Sponsors
- ADNOC Gas
- Capacity
- 1.5 million tonnes CO2 per year
- Technology
- Shell Cansolv amine capture with reinjection into deep geological reservoirs
- Capex
- USD 615 million EPC contract
- Offtake
- Not disclosed
What the sources establish
FID announced 6 September 2023. ADNOC states it will triple its carbon capture capacity to 2.3 Mt/yr. Expected start-up 2026.
Sources
Source: ADNOC · adnoc.ae · 2026 · Retrieved 26 August 2026