Projects · Offshore and onshore Abu Dhabi
Hail & Ghasha low-carbon gas development
FID taken 5 October 2023. ADNOC lists expected start-up in 2028. The hydrogen volume produced is not quantified in any ADNOC source and should not be assigned one.
Last verified:
Under constructionAs of 2028Confidence: High
- Location
- Offshore and onshore Abu Dhabi
- Sponsors
- ADNOC
- Capacity
- 1.5 Mt/yr CO2 capture; over 1.5 billion standard cubic feet per day of gas
- Technology
- Sour gas development with CCUS; low-carbon hydrogen produced to replace fuel gas
- Capex
- Part of USD 17 billion in EPC contracts awarded
- Offtake
- Not disclosed
What the sources establish
FID taken 5 October 2023. ADNOC lists expected start-up in 2028. The hydrogen volume produced is not quantified in any ADNOC source and should not be assigned one.
Sources
Source: ADNOC · adnoc.ae · 2028 · Retrieved 26 August 2026