Projects · Al Ruwais Industrial City, Abu Dhabi
TA'ZIZ low-carbon ammonia facility
Fertiglobe's 2025 Annual Report, published March 2026, states construction progressing to around 75% completion with production expected to commence in 2027. EPC awarded to Tecnimont (MAIRE Group) in May 2024; construction began Q3 2024. This plant is not operating. Equity percentages have never been disclosed by any partner.
Last verified:
- Location
- Al Ruwais Industrial City, Abu Dhabi
- Sponsors
- TA'ZIZ · Fertiglobe · GS Energy · Mitsui & Co.
- Capacity
- 1 million tonnes per annum of low-carbon ammonia
- Technology
- Ammonia from ADNOC-supplied hydrogen feedstock; up to 50% lower carbon intensity than conventional routes; CCS integration in phase 2
- Capex
- Under USD 500 million total capex (Fertiglobe 2025 Annual Report)
- Offtake
- Mitsui will offtake a certain volume for Japan and other Asian markets; GS Energy is an offtake partner. No volumes or tenor disclosed.
What the sources establish
Fertiglobe's 2025 Annual Report, published March 2026, states construction progressing to around 75% completion with production expected to commence in 2027. EPC awarded to Tecnimont (MAIRE Group) in May 2024; construction began Q3 2024. This plant is not operating. Equity percentages have never been disclosed by any partner.
Sources
Source: Fertiglobe · fertiglobe.com · March 2026 · Retrieved 26 August 2026
Source: fertiglobe.com · Retrieved 26 August 2026